- Main center blockERN 4,890,636.53
Adi Nfas Health Center
A new public health center for Adi Nfas — providing clinical services, maternal care, and community health support.
ApprovedSite preparationStage 2 of 4

Milestones
-
Stage 1ApprovedMay 2026Approved drawings3 drawing sheetsBills of quantities
-
2 Stage 2Site prepCurrent stageMay 2026At the Adi Nfas site — the people behind the project, and the open ground where the health center will be built.Read update
-
3 Stage 3ConstructionUpcoming
-
4 Stage 4OpeningTo be confirmed
Project funding
Public project
- Community contribution
- ERN 1,400,000
- Remaining documented minimum
- ERN 9,450,000+
At least the documented BOQs minus recorded community contributions. The waiting home and later cost changes are not included. This is not confirmed funding.
450 contributors · 12 countries
Updating the contribution total…
Components
View allCost plan
Cost planSee how the documented estimate is allocated · 10 packages · 3 source documents
ERN 10,844,391.83
Cost estimate, not money raised.
Where the cost goes
Tap a slice to see what it includes.
- Main center block45%
- Boundary and guard house18%
- Staff residence15%
- Site service systems13%
- Public toilets8%
- Waste incinerator1%
- Compound wallERN 1,632,793.40
- Guard houseERN 334,727.25
- Staff residenceERN 1,617,701.24
- Underground water reservoirERN 382,444.34
- Elevated water tankERN 140,560.37
- Septic tankERN 208,616.48
- Electrical worksERN 725,190.00
- Public toiletsERN 835,050.02
- Waste incineratorERN 76,672.20
Waiting home
The approved drawings show this scope, but none of the three BOQ scans contains a separate priced waiting-home package.
Excluded from the documented total.Source documents3 BOQ scans
Main center and staff residence BOQs
Main center on pages 1-4; staff residence on pages 5-8.
- Main center blockPages 1-4ERN 4,890,636.53
- Staff residencePages 5-8ERN 1,617,701.24
Document subtotalERN 6,508,337.77
Public facilities BOQs
Public toilets on pages 1-3; septic tank on page 4; guard house on pages 5-7; incinerator on pages 8-9.
- Public toiletsPages 1-3ERN 835,050.02
- Septic tankPages 4ERN 208,616.48
- Guard housePages 5-7ERN 334,727.25
- Waste incineratorPages 8-9ERN 76,672.20
Document subtotalERN 1,455,065.95
Water and site services BOQs
Underground reservoir on pages 1-2; elevated water tank on page 3; compound wall on pages 4-5; electrical works on pages 6-7.
- Underground water reservoirPages 1-2ERN 382,444.34
- Elevated water tankPages 3ERN 140,560.37
- Compound wallPages 4-5ERN 1,632,793.40
- Electrical worksPages 6-7ERN 725,190.00
Document subtotalERN 2,880,988.11
The compound-wall scan prints ERN 1,632,793.4; this record preserves that printed total as ERN 1,632,793.40. Its visible section subtotals differ by one cent.
Project details
Help build it
Contributions support the next stage of the health center.