Main center block

Primary health center building

Main center block — reference maquette visualization Open interactive 3D
Reference maquette visualization

An artistic interpretation of the Ministry's drawings — for understanding, not exact measurement

Report a correction
View cost breakdown

Cost breakdown

Where the money goes

Total · ERN4,890,636.53

Tap a trade to open its line items below

Full BOQ line items
A — Substructure Excavation and Earth Work ERN616,456.77
ItemDescriptionUnitQtyRateAmount
1.01 Clear off site to remove top vegetable or grassy soil to an average depth of 20cm m² 1,680.00 33.43 56,168.63
1.02 Footing excavation in ordinary soil not exceeding 150cm from stripped ground level m³ 112.65 1,099.10 123,813.34
1.03 Bulk excavation in ordinary soil to a depth not more than 100cm m³ 281.30 392.32 110,358.70
1.04 Back fill around foundation with good and selected excavated soil from site, rammed in layers not exceeding 20cm thick m³ 90.00 319.66 28,769.30
1.05 Selected and compacted soil under hard core to an average depth of 40cm, compacted to a layer of 20cm thick m³ 350.00 319.66 111,880.60
1.06 Cart away surplus excavated material to a distance not less than 1km from site m³ 35.00 235.18 8,231.22
1.07 25cm thick basaltic or equivalent stone hard core well rolled, consolidated and blinded with crushed stone to receive ground slab m² 620.00 285.86 177,234.99
Subtotal616,456.77
A — Substructure Concrete Work ERN995,440.81
ItemDescriptionUnitQtyRateAmount
2.01a Reinforced concrete C-25 360kg/m³ — in footing m³ 18.77 3,722.86 69,878.10
2.01b Reinforced concrete C-25 — in foundation column m³ 6.20 3,722.86 23,081.74
2.01c Reinforced concrete C-25 — in grade beam m³ 70.00 3,722.86 260,600.28
2.01d 10cm thick ground floor slab m² 620.00 372.29 230,817.39
2.01e 10cm thick C-15 mass concrete for pavement m² 58.00 372.29 21,592.59
2.02a Sawn zigba or steel form work — in footing m² 82.24 319.12 26,244.80
2.02b Form work — in foundation column m² 116.40 319.12 37,146.10
2.02c Form work — in grade beam m² 280.00 319.12 89,354.88
2.03a Reinforcement steel bar (cutting, bending, placing, tying) — 8mm Kg 406.10 46.32 18,811.64
2.03b Reinforcement steel bar — 10mm Kg 903.88 46.32 41,870.13
2.03c Reinforcement steel bar — 12mm Kg 3,568.34 49.33 176,043.15
Subtotal995,440.81
A — Substructure Masonry Work ERN1,012,258.09
ItemDescriptionUnitQtyRateAmount
3.01 50cm thick basaltic or equivalent stone foundation wall bedded in cement mortar mix 1:4 below NGL m³ 252.00 1,872.93 471,978.63
3.02 Ditto, roughly dressed above NGL to an average height of 50cm m³ 210.00 2,572.76 540,279.46
Subtotal1,012,258.09
B — Super Structure Concrete Work ERN1,134,929.88
ItemDescriptionUnitQtyRateAmount
1.01a Reinforced concrete C-25 360kg/m³ — in elevation column m³ 16.71 3,802.43 63,546.25
1.01b Reinforced concrete C-25 — in lintels m³ 4.00 3,802.43 15,209.73
1.01c Reinforced concrete C-25 — verandah tie beam m³ 17.12 3,802.43 65,097.64
1.01d Reinforced concrete C-25 — top roof tie beam m³ 20.75 3,802.43 78,900.47
1.02a Form work — in elevation column m² 322.32 352.45 113,602.46
1.02b Form work — in beams and lintels m² 60.00 352.45 21,147.14
1.02c Form work — verandah tie beam m² 171.20 352.45 60,339.85
1.02d Form work — top roof tie beam m² 166.00 352.45 58,507.10
1.03a Reinforcement steel bars — 8mm Kg 4,021.95 47.95 192,844.59
1.03b Reinforcement steel bars — 10mm Kg 4,553.46 50.47 229,792.46
1.03c Reinforcement steel bars — 12mm Kg 4,675.32 50.47 235,942.18
Subtotal1,134,929.88
B — Super Structure Block Work ERN576,371.24
ItemDescriptionUnitQtyRateAmount
2.01 20cm thick HCB wall bedded on cement sand mortar mix 1:4, both faces left for plastering m² 906.00 636.17 576,371.24
Subtotal576,371.24
B — Super Structure Water Proof Work ERN140,751.08
ItemDescriptionUnitQtyRateAmount
3.01 Supply & fix G-28 galvanized sheet roof covering per manufacturer instruction m² 110.40 793.96 87,652.90
3.02 Wooden purlin 5x7cm c/c ml 165.60 246.49 40,818.27
3.03 G-28 galvanized sheet gutters including all accessories (dev. length 40cm) Lm 13.80 406.68 5,612.13
3.04 PVC dia 110mm down pipe Lm 16.00 416.74 6,667.77
Subtotal140,751.08
B — Super Structure Steel Structure ERN23,544.86
ItemDescriptionUnitQtyRateAmount
4.03 Grill fence for windows (1.4x1.2)m pcs 6.00 3,924.14 23,544.86
Subtotal23,544.86
B — Super Structure Carpentry ERN66,848.43
ItemDescriptionUnitQtyRateAmount
5.01 Plywood ceiling, including 5x5cm wooden purlin spaced at 60x60cm, and wooden ristelli 3x1cm to cover joints m² 96.60 610.17 58,942.41
5.02 Hard board 25cm wide and 3cm thick for the gutters ml 27.60 286.45 7,906.02
Subtotal66,848.43
B — Super Structure Metal Work ERN91,006.09
ItemDescriptionUnitQtyRateAmount
6.01a Supply and fix metal sheet single-glazed doors/windows with ironmongery and lock — D1 (100x225 cm) Pcs 6.00 6,894.40 41,366.40
6.01b W1 (100x120 cm) Pcs 12.00 4,136.64 49,639.68
Subtotal91,006.09
B — Super Structure Finishing Work ERN184,005.32
ItemDescriptionUnitQtyRateAmount
7.01 Three coats of plaster with cement mortar to fine finish — internal wall surface m² 222.08 176.84 39,272.94
7.02 Plaster — external wall surface m² 242.90 176.84 42,954.78
7.03 Two coats of plaster in cement sand mix 1:3 to wall surface to receive ceramic tiles m² 5.00 134.11 670.57
7.04 Wall tiles, ceramic 15x15cm, polished with white cement grout m² 5.00 982.49 4,912.43
7.05 Terrazzo floor tiles bedded on cement sand mortar mix 1:3, joints grouted m² 96.60 893.29 86,291.92
7.06 10cm high ceramic skirting stuck to wall with cement sand mortar mix 1:3 backing Lm 52.00 190.44 9,902.67
Subtotal184,005.32
B — Super Structure Painting ERN49,023.96
ItemDescriptionUnitQtyRateAmount
8.01 Apply three coats of approved plastic wall paint to external and internal wall surface m² 347.00 85.39 29,631.79
8.02 Synthetic paint to internal wall surfaces up to 1.6m high from floor level m² 140.00 138.52 19,392.17
Subtotal49,023.96

Digitized from Ministry of Health, Engineering Division — Adi-Nfas Health Center New block BOQ