ማይ + ሓጽቢ / ማዕቆር ማይ ካብ ስእሊ ዝተወስደ ትርኢት
ማይ + ሓጽቢ / ማዕቆር ማይ · ካብ ስእሊ ዝተወስደ ትርኢት

ዝርዝር ወጻኢ

ጠቕላላ · ERN382,444.34
A — Substructure Excavation and Earth Work ERN138,079.05
ItemDescriptionUnitQtyRateAmount
1.01 Clear off site to remove top vegetable or grassy soil to an average depth of 20cm 22.45 33.43 750.59
1.02 Excavate in bulk to a depth not exceeding 300cm, starting from natural ground level 77.28 1,538.74 118,913.57
1.03 Back fill around the wall with good and selected excavated material 12.50 319.66 3,995.74
1.04 Cart away surplus excavated material to a distance not less than 1km from site 30.00 235.18 7,055.33
1.05 25cm thick basaltic or equivalent stone hard core, well rolled and blinded to receive ground slab 25.76 285.86 7,363.83
Subtotal138,079.05
A — Substructure Concrete Work ERN210,026.47
ItemDescriptionUnitQtyRateAmount
2.01 Lean concrete C-5 150kg/m³, 5cm thick under bottom slab 25.76 135.09 3,479.95
2.02a Reinforced concrete C-25 360kg/m³ — in 15cm thick bottom slab 25.76 1,116.86 28,770.27
2.02b Reinforced concrete C-25 — in 15cm thick side walls 61.20 1,116.86 68,351.73
2.02c Reinforced concrete C-25 — in 15cm thick top slab 25.76 1,116.86 28,770.27
2.03a Sawn zigba or steel form work — in 15cm thick top slab 20.00 319.12 6,382.49
2.03b Form work — in 15cm thick side walls 61.20 319.12 19,530.42
2.04a Reinforcement steel bar — 10mm Kg 790.97 49.33 39,022.30
2.04b Reinforcement steel bar — 8mm Kg 318.62 49.33 15,719.04
Subtotal210,026.47
A — Substructure Finishing Work ERN32,538.82
ItemDescriptionUnitQtyRateAmount
3.01 Three coats of plaster with cement mortar to fine finish — internal surface of side walls, floor and roof 184.00 176.84 32,538.82
Subtotal32,538.82
A — Substructure Metal Work ERN1,800.00
ItemDescriptionUnitQtyRateAmount
4.01 Metallic sheet cover for an inspection opening 60x60cm including metallic frames, hinges and locker pcs 1.00 1,800.00 1,800.00
Subtotal1,800.00

ካብ ዝተወስደ Ministry of Health, Engineering Division — Adi-Nfas Health Center underground water reservoir 50 m³