Adi Nfas Health Center

ApprovedSite preparation (2 of 6)

Static public project record for the planned Adi Nfas Health Center.

Reference visualization of the planned Adi Nfas Health Center compound — central clinic block with a red cross, completed roofs, staff and service buildings, and below-grade septic and water-reservoir cutaways within the perimeter wall.

What is being built

Explore components

Overview

Where the build stands

  1. Approval
  2. Site prep
  3. Foundation
  4. Structure
  5. Services
  6. Opening

1 of 6 stages · now building: Site preparation

Where the budget goes

at a glance
  • Main center45%
  • Boundary + guard18%
  • Staff residence15%
  • Site services13%
  • Public toilets8%
  • Incinerator1%

Rounded from verified BOQ package totals. Source PDFs bundle multiple BOQs, so this is not a component-by-component claim.

Milestones

  1. Approval May 2026
  2. Site prep In progress
  3. Foundation Upcoming
  4. Structure Upcoming
  5. Services Upcoming
  6. Opening To be confirmed

Documents

  • Architectural & Structural DrawingsSheets · 14
  • New center block BOQ8 scans · includes staff residence BOQ
  • Public toilets BOQ9 scans · includes toilets, septic, guard house, incinerator
  • Underground reservoir 50m37 scans · includes reservoir, wall, electrical works

Photos

At the Adi Nfas site — the people behind the project, and the open ground where the health center will be built.
At the Adi Nfas site — the people behind the project, and the open ground where the health center will be built. · May 2026
Open ground at Adi Nfas, the village beyond — before construction begins.
Open ground at Adi Nfas, the village beyond — before construction begins. · June 2026

Updates

  • Site preparation

    At the Adi Nfas site — the people behind the project, and the open ground where the health center will be built.

    May 2026
  • Site preparation

    Open ground at Adi Nfas, the village beyond — before construction begins.

    June 2026