- Main center blockERN 4,890,636.53
Adi Nfas Health Center
A new public health center for Adi Nfas — providing clinical services, maternal care, and community health support.
ApprovedSite preparationStage 2 of 4
Help build it
Contributions support the next stage of the health center.
Milestones
-
Stage 1ApprovedMay 2026Approved drawings3 drawing sheetsBills of quantities
-
2 Stage 2Site prepCurrent stage
May 2026 · June 2026 · 5:57 Clearing the ground and staking out the compound before foundation work begins. Read update -
3 Stage 3ConstructionUpcoming
-
4 Stage 4OpeningTo be confirmed
Components
View allCost plan
Cost planSee how the documented estimate is allocated · 10 packages · 3 source documents
ERN 10,844,391.83
Cost estimate, not money raised.
Where the cost goes
Tap a slice to see what it includes.
- Main center block45%
- Boundary and guard house18%
- Staff residence15%
- Site service systems13%
- Public toilets8%
- Waste incinerator1%
- Compound wallERN 1,632,793.40
- Guard houseERN 334,727.25
- Staff residenceERN 1,617,701.24
- Underground water reservoirERN 382,444.34
- Elevated water tankERN 140,560.37
- Septic tankERN 208,616.48
- Electrical worksERN 725,190.00
- Public toiletsERN 835,050.02
- Waste incineratorERN 76,672.20
Waiting home
The approved drawings show this scope, but none of the three BOQ scans contains a separate priced waiting-home package.
Excluded from the documented total.Source documents3 BOQ scans
Main center and staff residence BOQs
Main center on pages 1-4; staff residence on pages 5-8.
- Main center blockPages 1-4ERN 4,890,636.53
- Staff residencePages 5-8ERN 1,617,701.24
Document subtotalERN 6,508,337.77
Public facilities BOQs
Public toilets on pages 1-3; septic tank on page 4; guard house on pages 5-7; incinerator on pages 8-9.
- Public toiletsPages 1-3ERN 835,050.02
- Septic tankPages 4ERN 208,616.48
- Guard housePages 5-7ERN 334,727.25
- Waste incineratorPages 8-9ERN 76,672.20
Document subtotalERN 1,455,065.95
Water and site services BOQs
Underground reservoir on pages 1-2; elevated water tank on page 3; compound wall on pages 4-5; electrical works on pages 6-7.
- Underground water reservoirPages 1-2ERN 382,444.34
- Elevated water tankPages 3ERN 140,560.37
- Compound wallPages 4-5ERN 1,632,793.40
- Electrical worksPages 6-7ERN 725,190.00
Document subtotalERN 2,880,988.11
The compound-wall scan prints ERN 1,632,793.4; this record preserves that printed total as ERN 1,632,793.40. Its visible section subtotals differ by one cent.
Support from 12 countries
Rounded totals in local currencies.
- Canada CAD 11,000.00USD 1,000.00
- Denmark DKK 12,000.00
- Germany EUR 14,000.00
- Netherlands EUR 4,000.00
- Norway NOK 142,000.00
- Saudi Arabia SAR 6,000.00
- Sweden SEK 141,000.00
- Switzerland CHF 9,000.00
- United Kingdom GBP 13,000.00
- Other locations3 countries grouped
Updated · 2026-07-10