Adinfas, Zoba Maekel · Adinfas Health Center

Milestones

Approved · May 2026 · Next: Site preparation

  1. Approval complete May 2026 Approved plans, drawings, and BOQ packages are documented for the public record. Next → Site preparation
  2. 2Site preparation In progress Clearing, layout, and compound preparation before foundation work begins. Next → Foundation
  3. 3Foundation Upcoming Footings and foundations for the main center block and support buildings. Next → Structure + roof
  4. 4Structure + roof Upcoming Structural frame, walls, and roof completion across the compound buildings. Next → Services + finishing
  5. 5Services + finishing Upcoming Water, septic, electrical services, and interior finishing works. Next → Opening
  6. 6Opening To be confirmed Clinic handover and public opening once construction and commissioning are confirmed.